Russia: Severstal has ordered four Inba slag granulation plants with dynamic dewatering of the slag sand from Paul Wurth as part of a contract for design and supply of technology and equipment for the reline of Blast Furnace No. 5 ‘Severyanka’ at Cherepovets Metallurgical Plant. Severstal’s installations will be the first use of this technology in Russia.
“The fifth blast furnace has been operating for over 14 years and this refurbishment project is expected to more than double its lifespan," said Alexander Shevelev, chief executive officer of Severstal.
The order also includes a Bell Less Top charging system with a hopper volume of 80m3 and a chute transmission gearbox with a pressurised cooling system. The blast furnace top gas will be cleaned by a Paul Wurth two-stage top gas cleaning plant. Auxiliary facilities at the plant will be built in 2018 and 2019 and the main equipment will be installed in 2020.